View 001
The materials start here in the mill, where the mortise and tenon joinery posts and beams are shaped to become a home.
View 002
View 003
View 004
At the site during the first pouring of the foundation, a marking in the mud.
View 005
After laying the initial foundation, the radiant flooring system is established.
View 006
The perimeter system which appears here redirects ground moisture away from the foundation.
View 007
A vapor barrier, and insulation is placed over the entire foundation.
View 008
With vapor barrier and insulation in place, the final network of tubing is placed which will aid the entire radiant flooring system to protect the house from moisture and cold.
View 009
The foundation is then ready for the main slab to be poured.
View 010
The foundation is then ready for the main slab to be poured.
View 011
Frame Raising begins 8:05AM, October 26, 1998. Here the first wall is constructed, and support braces are put in place.
View 012
One of the owners, Eric Flo, assists in the frame raising.
View 013
View 014
The Purlin frame begins to take shape and reaches completion.
View 015
To ensure the frame is completely level, plumb, and square, these "Come alongs" are used before the "Pegs" are inserted at the joints.
View 016
 